Wye Valley Group – Vehicle Workshop Flooring
The 788sq metre Workshop had a newly laid concrete floor, however in order to lay the two-coat epoxy resin flooring system, the floor required preparation.
Due to the fact that moisture readings taken at multiple points over the floor, showing readings at between 230 to 240 the newly laid concrete floor was given a coat of Damp Proof Membrane epoxy resin primer in order to prevent residual damp left in the concrete rising and delaminating the epoxy flooring system. Once the primer was completely dry the two coat Resdev Pumatect high build, epoxy resin flooring system was laid in the clients chosen light grey.
Finally a 200mm wide demarcation line was installed around two pit areas and Rolling Roads in Resdev Pumatect high build, epoxy resin flooring, safety yellow.