Amesplan Limited – Warehouse Flooring
The process involved a heavy shot blast – double the average strength in order to remove the worst of the surface as there was 2-3mm asphalt on circa 400 square meters that required a second pass. To prevent damp ingress two coats of DCP DPM epoxy resin priming system were laid before 35 tonnes of DCP renovation base screed giving the whole area a covering of 10mm to 70mm to achieve a minimum 7-8mm screed. 20 tonnes of DCP Cemflow topping cementitious screed were laid completing the concrete slab renovation. To complete the flooring transformation two coats of Resdev Pumatect, high build epoxy resin flooring system were laid in the clients chosen Mid Grey.
The job was spread over 4 weeks to fall in line with the clients building work schedule.